INSP-Final Inspection | 3/26/2014 | 3/27/2014 | 3/27/2014 | A | PASS |
Forrest France
|
|
|
Functional testing and final inspection passed. Previous C/N items finished. Fire sprinkler permit finaled.
|
INSP-Final Inspection | 3/26/2014 | 3/26/2014 | 3/26/2014 | P | DEFR |
Forrest France
|
|
|
Scheduled in conjunction with related permit finals 3/27.
|
INSP-Final Inspection | 3/24/2014 | 3/25/2014 | 3/25/2014 | A | NR |
Forrest France
|
|
|
Missing riser finish pack including calc stickers, DCVA certification, caps at FDC, sign at outside bell, riser tag, etc., need to complete forward flow, missing escutcheons.
|
INSP-Sprinkler Rough-in | 3/6/2014 | 3/6/2014 | 3/6/2014 | P | PART |
Forrest France
|
|
|
Overhead work at the grid ceiling areas completed to date okay for cover. Flex heads at some locations are not perpendicular to the ceiling and will need adjustment.
|
INSP-Sprinkler Rough-in/Hydro | 2/13/2014 | 2/14/2014 | 2/14/2014 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic testing passed. Noted spacing adjustments will be necessary at the east side offices and classrooms.
|
INSP-Sprinkler Rough-in | 1/27/2014 | 1/27/2014 | 1/27/2014 | P | PART |
Forrest France
|
|
|
UG fire supply line and post indicator including stub-in approved for cover.
|