Permit Information
Permit NumberFIR13-00725
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 1000 W MYRTLE ST
Project NameJUMP Building
Customer Number 
ePlanReviewYes
Description
Connect to existing below grade garage fire pump supply piping and extend a new standpipe system and wet and dry systems to protect the above grade areas of the new 6 story JUMP building in accordance with NFPA 13 and 14 for light and ordinary hazards.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/8/20157/10/20157/10/2015APASS
DetailsThomas Walsh
Completion of fire alarm interface for Jump Bldg (above parking garage), including 5th and 6th floor wet pipe waterflows, tampers, etc.
Test of 6 dry-pipe valves supplying standpipes for exit stairs in the above ground parking garage - three located at grade level, and three located in the lower parking garage. All six tested satisfactorily, including low-air alarms and waterflow alarms. All six dry pipe valves were trip tested to ensure proper operation.
NOTE: U/G parking and Helix systems are on a separate permit.
INSP-Sprinkler Rough-in/Hydro7/9/20157/9/20157/9/2015PPART
DetailsThomas Walsh
Test of wet and dry pipe fire sprinkler systems, including fire alarm interface, including tampers, waterflows, low-air tests and dry pipe valve trip tests for A/G parking garage (levels 1 thru 5) and associated wet systems, including Makers room and 5th floor wet system.
All dry-pipe and wet pipe systems alarmed within 60 seconds. All other fire alarm interface signals came in OK.
NOTE: U/G parking garage under separate permit, and not tested this visit. Fire pump is also under this other permit (U/G PG).
INSP-Sprinkler Rough-in/Hydro7/6/20157/6/20157/6/2015PPASS
DetailsThomas Walsh
Hydrotest of dry pipe valve supplying standpipe for stair A01, which is located in the above grade parking garage.
PASSED
INSP-Sprinkler Rough-in/Hydro7/1/20157/1/20157/1/2015PPASS
DetailsThomas Walsh
Hydrotest of two (2) dry pipe systems supplying upper standpipes located at stairs C2, A03, A03B, and A04. (200 psi @ 2hrs - PASSED).
INSP-Sprinkler Rough-in6/30/20156/30/20156/30/2015PPASS
DetailsThomas Walsh
Hydrotest of first fllor dry pipe system protecting A/G parking garage (around Helix). 200 psi @ 2 hours - PASSED
INSP-Sprinkler Rough-in6/29/20156/30/20156/30/2015ACANC
DetailsThomas Walsh
Wrong permit number for this inspection. See FIR13-00167 for FS U/G hydrotest inspection this date.
INSP-Sprinkler Rough-in/Hydro6/11/20156/11/20156/11/2015PPASS
DetailsThomas Walsh
Hydrotest of wet pipe system protecting Makers Room at the top level of the parking garage - 200 psi @ 2 hours - PASSED
INSP-Sprinkler Rough-in/Hydro5/18/20155/19/20155/19/2015APASS
DetailsThomas Walsh
Hydrotest of Helix thrid floor dry system, which includes helix ramp, multimedia room and inspiration room, with mechanical room above. Found one (1) obstructed A/S in lobby of multimedia room that will have to be extended below surface mounted light. No other discrepncies noted.
INSP-Supply line flush5/5/20155/7/20155/6/2015ACANC
DetailsScott Arellano
Jeff is your contact on site. Please call 1/2 hour prior to inspection. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in/Hydro5/5/20155/6/20155/6/2015ACANC
DetailsScott Arellano
Inspection cancelled by contractor again because system not holding pressure.
INSP-Sprinkler Rough-in5/5/20155/5/20155/6/2015PCANC
DetailsScott Arellano
Inspection cancelled by contractor because system not holding pressure.
INSP-Sprinkler Rough-in4/24/20154/27/20154/27/2015APART
DetailsKatie Marron
Dry pipe stub ups for FDC and Test header off of myrtle street ok to be wrapped and covered.
INSP-Sprinkler Rough-in1/23/20151/26/20151/26/2015PPART
DetailsForrest France
Completed OH rough-in for work finished to date at the first floor parking garage area B and C. Ref. plan sheets FP7 and FP8.
INSP-Sprinkler Rough-in1/8/20151/9/20151/9/2015APART
DetailsForrest France
Completed rough-in inspection for the 2nd floor helix dry system- refer to initialed plan sheet FP 15.
INSP-Sprinkler Rough-in1/5/20151/6/20151/8/2015PPART
DetailsForrest France
Completed rough-in inspection for the 3rd floor heilix- sheet FP 16. Refer to plans for dated annotations. Missing one hanger at 4" main.
INSP-Sprinkler Rough-in1/5/20151/6/20151/5/2015PCANC
DetailsForrest France
2nd floor Helix. Mike S is your contact. Please call 1/2 hour prior to inspection. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in/Hydro1/5/20151/6/20151/5/2015PCANC
DetailsForrest France
Inspection to be on the 3rd floor, please call 1/2 hour prior to inspection. Mike S is your contact. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in12/19/201412/22/201412/22/2014PPART
DetailsForrest France
INSP-Sprinkler Rough-in/Hydro12/19/201412/22/201412/19/2014PCANC
DetailsForrest France
Inspection is on the 3rd floor. Mike S. is your contact. Please call 1/2 hour prior to inspection. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in12/12/201412/15/201412/18/2014PPART
DetailsForrest France
Rough-in inspection at the imagination room finished- provide plans reflecting deletion of upright coverage.
INSP-Sprinkler Rough-in12/17/201412/18/201412/18/2014PPART
DetailsForrest France
Completed rough-in inspection at the 4th floor plan sheet FP17. Items noted include; obstructed ECU at the filing room, missing coverage at a closet not shown on plan adjacent to a storage room, overspaced ECU at two locations within the heilix, provide pendent at new drop ceiling formerly OTS, relocate upright sprinkler at the center storage room A23 to meet design spacing. Locations marked on plan set.
INSP-Sprinkler Rough-in12/16/201412/17/201412/18/2014APART
DetailsForrest France
Inspection for basement level feed mains completed to date.
INSP-Sprinkler Rough-in12/15/201412/16/201412/17/2014PPART
DetailsForrest France
Completed rough-in inspection at the 5th floor level plan sheet FP-18. Items noted include; blocked upright coverage at an electrical room, EC upright in contact with a wall, separation distance at two EC uprights is not met, drum drip at the dry system remote end is not accessible, field modifications at remote area 3 include an additional branchline and added pendent heads at the perimeter soffits, provide label at relocated dry system inspectors test, construction at the elevator lobby bay doors and concealed space incomplete, need to remove foil at uprights once painting is finished. Refer to dated plan annotations.
INSP-Sprinkler Rough-in11/12/201411/13/201411/13/2014APART
DetailsForrest France
Rough-in okay for cover at the 1st and 2nd floor kitchen elevator lobby ceilings. Standpipe at the 1st thru 3rd floor levels NE stair also inspected for cover at the landing ceiling- discussed plan modification and alternate approval regarding location of hose valves at this stairway.
INSP-Sprinkler Rough-in10/9/201410/10/201410/10/2014APASS
DetailsTroy Cobbley
Rough to cover passed for 4th floor Bathrooms and the 3rd floor Hallway as marked on the city approved plans with todays date.
INSP-Conference9/24/20149/24/20149/24/2014ADONE
DetailsForrest France
INSP-Sprinkler Rough-in12/18/201412/19/2014 P 
DetailsForrest France
The inspection is on the 4th floor. Mike S is your contact. Please call 1/2 hour prior to inspection Phone #: ###-#### >> Inspection requested via web by Stan Beus