INSP-Final Inspection | 4/13/2015 | 4/13/2015 | 4/13/2015 | P | PASS |
Katie Marron
|
|
|
Remainder of fire alarm work completed. Inspection of flow and tamper switch pass. Fire Alarm Bell connection fixed on sight.
|
INSP-Alarm Testing | 10/1/2014 | 10/1/2014 | 10/1/2014 | P | DONE |
Troy Cobbley
|
|
|
Fire alarm complete in the new hanger. 110 power at the elevator and door mag has been repaired.
|
INSP-Final Inspection | 9/26/2014 | 9/26/2014 | 9/26/2014 | P | FAIL |
Troy Cobbley
|
|
|
To complete the fire alarm in the new area I need the 110 power of the elevator monitored and the door mags to release upon general alarm.
|
INSP-Sprinkler Rough-in/Hydro | 9/24/2014 | 9/25/2014 | 9/26/2014 | P | CANC |
Troy Cobbley
|
|
|
Canceled due to time constraints
|
INSP-Final Inspection | 9/11/2014 | 9/12/2014 | 9/12/2014 | A | FAIL |
Troy Cobbley
|
|
|
Items test today included tamper switches for the backflow, hose valve and new hanger riser. Also included were the new hanger flow switch, smoke, pull, phone lines and loss of a/c. Elevator and riser to existing building is not complete. Need breaker lock and breaker identified. Electric alarm bell not installed yet.
|