INSP-Final Inspection | 4/8/2014 | 4/8/2014 | 4/8/2014 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 4/4/2014 | 4/7/2014 | 4/7/2014 | P | PEND |
Forrest France
|
|
|
Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 4/1/2014 | 4/2/2014 | 4/2/2014 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic retest passed, verified previous correction items. Final pending project finishes and trade related work.
|
INSP-Final Inspection | 3/31/2014 | 4/1/2014 | 4/1/2014 | P | NR |
Forrest France
|
|
|
C/N items pending, visible leakage and pressure loss at the guage during hydro test, project finishes and remodel work underway.
|
INSP-Sprinkler Rough-in/Hydro | 3/31/2014 | 4/1/2014 | 4/1/2014 | P | FAIL |
Forrest France
|
|
|
Noted corrections include; provide matched temp heads at the first floor mens restroom, provide QR head in the 1st floor storage room, two heads at the glass area exceed min. spacing, combustible concealed space adjacent to the south stairway is not protected, repair leak at the storage closet 1st floor, provide thermal barrier at the dry pendent SW entry.
|