INSP-Final Inspection | 8/4/2014 | 8/5/2014 | 8/5/2014 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 7/25/2014 | 7/28/2014 | 7/28/2014 | A | FAIL |
Craig D. Hanson
|
|
|
System is not functioning correctly, not tied into the pre-action valves. Morgan states he needs to do a plan Mod so that more relays can be added.
|
INSP-Alarm Testing | 7/24/2014 | 7/25/2014 | 7/25/2014 | A | FAIL |
Troy Cobbley
|
|
|
The fire sprinkler contractor did not call for a final for his items and is needed to test the tamper and pressure switches on the new dry systems. No inspection performed.
|