INSP-Final Inspection | 12/3/2014 | 12/4/2014 | 12/4/2014 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Alarm Testing | 12/3/2014 | 12/3/2014 | 12/3/2014 | A | DONE |
Troy Cobbley
|
|
|
Finished except for the supervisory signals, low air and tamper, from the pre-action system.
|
INSP-Alarm Testing | 8/18/2014 | 8/19/2014 | 8/19/2014 | A | DONE |
Troy Cobbley
|
|
|
Fire alarm in the Locker Rooms/Storage/PACU areas is complete.
|
INSP-Alarm Testing | 8/15/2014 | 8/18/2014 | 8/18/2014 | A | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for locations where minor corrections and retesting are required.
|
INSP-Alarm Testing | 8/13/2014 | 8/15/2014 | 8/15/2014 | A | PART |
Craig D. Hanson
|
|
|
Rough in OK. Phase 2 complete. Could not test alarms no pre-tested inspection documention.
|
INSP-Alarm Testing | 8/11/2014 | 8/14/2014 | 8/13/2014 | A | CANC |
Troy Cobbley
|
|
|
As early as possible Phone #: 2089411846 >> Inspection requested via mobile web by Brian A Inspection cancelled via mobile web on Wednesday, August 13, 2014.
|
INSP-Alarm Testing | 6/23/2014 | 6/24/2014 | 6/24/2014 | A | DONE |
Troy Cobbley
|
|
|
Lab, Equipment Room and Lobby fire alarm is complete.
|