INSP-Final Inspection | 11/21/2014 | 11/24/2014 | 11/24/2014 | A | PASS |
Forrest France
|
|
|
Scope of fire sprinkler work at the new lab completed. Mains and branchlines extending to the next phase are installed, however drop ceilings and pendent heads are not yet provided.
|
INSP-Final Inspection | 11/19/2014 | 11/20/2014 | 11/20/2014 | A | CANC |
Forrest France
|
|
|
Please meet in B.25 plan review room Phone #: ###-#### >> Inspection requested via web by John Wheeler Inspection cancelled from web by: John Wheeler
|
INSP-Sprinkler Rough-in/Hydro | 10/8/2014 | 10/9/2014 | 10/9/2014 | A | PART |
Forrest France
|
|
|
Overhead rough-in completed. Need to provide additional coverage at the open area adjacent to the QRA tech room. Drops and sprinklers are not yet installed. Initial hydrostatic test also completed.
|