INSP-Final Inspection | 12/29/2014 | 12/30/2014 | 12/30/2014 | A | PASS |
Forrest France
|
|
|
Scope of work completed. Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 12/29/2014 | 12/30/2014 | 12/30/2014 | A | PART |
Forrest France
|
|
|
UG fire supply line passed hydrostatic test.
|
INSP-Sprinkler Rough-in/Hydro | 9/9/2014 | 9/11/2014 | 9/10/2014 | A | CANC |
Forrest France
|
|
|
Jeff is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Supply line flush | 9/4/2014 | 9/5/2014 | 9/5/2014 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed. Alot of rust in line
|
INSP-Sprinkler Rough-in | 6/27/2014 | 6/27/2014 | 6/27/2014 | P | PART |
Forrest France
|
|
|
Fire supply line including the IBR and PIV okayed for bury.
|
INSP-Sprinkler Rough-in | 6/26/2014 | 6/27/2014 | 6/27/2014 | A | CANC |
Forrest France
|
|
|
This is an ug to cover. Bryan is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 6/19/2014 | 6/20/2014 | 6/19/2014 | A | CANC |
Forrest France
|
|
|
This is an ug to cover. Bryan is the contact.Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|