INSP-Final Inspection | 11/24/2015 | 11/25/2015 | 11/25/2015 | A | PASS |
Jim Page
|
|
|
FIre sprinkler inspections completed on 12/30/2014 under FIR14-00363, all inspections complete for fire sprinklers.
|
INSP-Final Inspection | 12/30/2014 | 12/31/2014 | 12/31/2014 | A | PART |
Forrest France
|
|
|
Need to adjust PIV tamper and flow switch at the system riser 1st floor. Remainder of inspection passed.
|
INSP-Final Inspection | 12/29/2014 | 12/30/2014 | 12/30/2014 | A | PART |
Forrest France
|
|
|
Final pending sprinkler monitoring and associated fire alarm work. Remainder of C/N items finished.
|
INSP-Sprinkler Rough-in/Hydro | 12/29/2014 | 12/30/2014 | 12/30/2014 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test completed and passed for both new wet systems.
|
INSP-Final Inspection | 12/29/2014 | 12/29/2014 | 12/29/2014 | P | PEND |
Forrest France
|
|
|
Jeff C. is your contact ###-####. Please call 1/2 hour prior to inspection. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 12/23/2014 | 12/23/2014 | 12/26/2014 | P | NR |
Forrest France
|
|
|
|
INSP-Final Inspection | 12/19/2014 | 12/22/2014 | 12/22/2014 | A | FAIL |
Forrest France
|
|
|
C/N items include; missing coverage at the shell space first floor near exit door, overspaced upright coverage at the 2nd floor west side, missing seismic bracing at the top of the 4" feed main 2nd floor, ceiling tile and escutcheons yet to be installed in some areas of the 1st floor, need finish pack at the riser, permit activity notes do not indicate a hydrostatic test for the OH or UG has been completed.
|
INSP-Sprinkler Rough-in/Hydro | 10/30/2014 | 10/31/2014 | 10/31/2014 | P | FAIL |
Craig D. Hanson
|
|
|
heads need to installed in fireplace chase's. head needs installed in new room 1st floor S unit. As builts need to be submitted. Re-hydro after instilation of heads.
|
INSP-Sprinkler Rough-in | 10/28/2014 | 10/28/2014 | 10/28/2014 | P | PART |
Forrest France
|
|
|
Okay to cover sheetrock lids as noted.
|
INSP-Sprinkler Rough-in | 10/1/2014 | 10/2/2014 | 10/2/2014 | P | PART |
Forrest France
|
|
|
Overhead work okayed for cover at three restrooms, med gas room, and two soffits with sheetrock lids 1st floor as marked and dated on approved plans. Also discussed FDC location.
|
INSP-Sprinkler Rough-in | 9/9/2014 | 9/11/2014 | 9/9/2014 | A | CANC |
Forrest France
|
|
|
Jeff is the contact.Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|