Permit Information
Permit NumberFIR14-00474
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 2653 S VICTORY VIEW WAY
Project NameInvlota Data Center
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of adding a double interlock preaction system, a supply for a future double interlock preaction system and a wet system. The preaction system is a double tree supplied through 6” underground and a 6” header. The tree is a grid type layout.

The underground was installed under permit FIR14-00325

(INVOLTA DATA CENTER) This submittal is for tenant improvement construction permit. Civil and Structural Footing/Foundation/Steel packages were previously submitted and approved under separate permits.

Project is for a new, single-story, 31,460 square foot data center and office tenant, with future 15,400 square foot Phase 2 (to be permitted separately at future date). This building will provide secure data storage for multiple customers. The facility will be staffed 24 hours a day, 7 days a week. Work to include...

Contractor’s Note:
The building permit has not been issued at this time. The building department may determine that changes are required to the building plans in order to meet code. The changes may affect the sprinkler system. The sprinkler contractor will be obligated to make all necessary changes that may be required. Therefore, if the sprinkler contractor chooses to proceed without an issued building permit, they will do so on their own cognizance. This note does not constitute an early start agreement.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/22/201412/22/201412/22/2014APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection12/18/201412/19/201412/19/2014ACANC
DetailsTroy Cobbley
Rick Phone #: ###-####
INSP-Final Inspection12/17/201412/18/201412/19/2014ACANC
DetailsTroy Cobbley
Bernie, the general contractor, wanted life safety a priority so sprinkler inspection is being canceled.
INSP-Final Inspection12/17/201412/17/201412/17/2014PPART
DetailsTroy Cobbley
Forward flush passed. No other testing performed due to fire alarm communication problems.
INSP-Sprinkler Rough-in/Hydro12/16/201412/16/201412/16/2014PPASS
DetailsTroy Cobbley
North east room ceiling ok to install.
INSP-Sprinkler Rough-in11/25/201411/25/201411/25/2014PPASS
DetailsTroy Cobbley
Remaining ceilings are ok to install.
INSP-Sprinkler Rough-in/Hydro11/13/201411/13/201411/13/2014PPASS
DetailsTroy Cobbley
See the city approved plans for additional rooms where piping can be covered.
INSP-Sprinkler Rough-in/Hydro11/7/201411/10/201411/10/2014APASS
DetailsTroy Cobbley
24hr air test passed
INSP-Sprinkler Rough-in/Hydro11/6/201411/7/201411/7/2014APASS
DetailsTroy Cobbley
Overhead hydro test passed
INSP-Sprinkler Rough-in/Hydro11/5/201411/6/201411/6/2014ADEFR
DetailsForrest France
Overbooked
INSP-Sprinkler Rough-in/Hydro10/23/201410/23/201410/23/2014PPASS
DetailsTroy Cobbley
Remaining hardlids ok to be installed and cover piping
INSP-Sprinkler Rough-in10/20/201410/20/201410/20/2014PPASS
DetailsTroy Cobbley
See the city approved plans for locations where piping above the hardlids can be covered. I also performed a rough-in inspection for the remaining overhead piping. Additional cover inspections will be required.
INSP-Sprinkler Rough-in9/9/20149/10/20149/10/2014APASS
DetailsTroy Cobbley
See the city approved plans for "Entry" marked on the plans as OK to cover.
INSP-Sprinkler Rough-in9/4/20149/4/20149/4/2014PPASS
DetailsTroy Cobbley
See the city approved plans for area clouded in red where rough-in is passed. Noted uprights slightly overspaced in small Storage Room.
INSP-Sprinkler Rough-in/Hydro8/14/20148/14/20148/14/2014PPART
DetailsForrest France
UG fire supply line passed hydrostatic testing within allowable leakage per NFPA 13.