INSP-Final Inspection | 9/2/2015 | 9/3/2015 | 9/3/2015 | A | PASS |
Thomas Walsh
|
|
|
Final inspection of the fire service U/G supply to the building - PASSED. Contractor cert. of completion signed off and will be emailed to the PDS office.
|
INSP-Sprinkler Rough-in/Hydro | 2/19/2015 | 2/23/2015 | 2/23/2015 | A | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic test completed acceptable.
|
INSP-Supply line flush | 2/18/2015 | 2/19/2015 | 2/19/2015 | P | PART |
Forrest France
|
|
|
UG fire supply line flush completed satisfactory.
|
INSP-Sprinkler Rough-in | 2/10/2015 | 2/12/2015 | 2/12/2015 | P | NR |
Forrest France
|
|
|
UG/Flush. Jeff C is your contact. Please call 1/2 hour prior to inspection. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 2/10/2015 | 2/11/2015 | 2/11/2015 | P | CANC |
Forrest France
|
|
|
UG/Hydro. Jeff C is your contact. Please call 1/2 hour prior to inspection. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 2/10/2015 | 2/11/2015 | 2/10/2015 | P | CANC |
Forrest France
|
|
|
UG/Flush inspection. Jeff C is your contact. Please call 1/2 hour prior to inspection. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 10/13/2014 | 10/13/2014 | 10/13/2014 | P | PASS |
Craig D. Hanson
|
|
|
|