INSP-Final Inspection | 1/8/2015 | 1/9/2015 | 1/9/2015 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. Rob to submitt for work to remove the large vesda system that is currently shown on the city approved plans.
|
INSP-Final Inspection | 12/23/2014 | 12/23/2014 | 12/23/2014 | P | PART |
Troy Cobbley
|
|
|
A temporary for the fire alarm permit only is being given with scotts approval until the large Vesda system has been calibrated/inspected and the dust covers have been removed from all detectors.. Will need the NFPA record of completion forms as well.
|
INSP-Alarm Testing | 12/19/2014 | 12/22/2014 | 12/22/2014 | A | DONE |
Troy Cobbley
|
|
|
Continued testing on the fire alarm system which included the fire sprinkler system interconnections. I noted several overspaced strobes and discussed the Man Trap door operation.
|
INSP-Final Inspection | 12/18/2014 | 12/19/2014 | 12/19/2014 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Robb Phone #: ###-####
|
INSP-Final Inspection | 12/16/2014 | 12/17/2014 | 12/17/2014 | P | CANC |
Troy Cobbley
|
|
|
Communication was down so no inspection was performed. Jonothan Phone #: ###-####
|
INSP-Alarm Testing | 12/9/2014 | 12/10/2014 | 12/11/2014 | P | DONE |
Troy Cobbley
|
|
|
Inspected/tested audio/visuals for the "industrial" portion of the building. Also did unit shut down. Need as-builts reflecting changes of a/v's from ceiling mount to wall mount and gererator power.
|