INSP-Final Inspection | 1/19/2016 | 1/20/2016 | 1/20/2016 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 2/3/2015 | 2/4/2015 | 2/4/2015 | A | FAIL |
Troy Cobbley
|
|
|
Waiting for hvac units to be repaired or removed so the remaining duct detectors can be tested for shutdown.
|
INSP-Final Inspection | 2/2/2015 | 2/3/2015 | 2/3/2015 | A | FAIL |
Troy Cobbley
|
|
|
The FACP, fire sprinkler devices, batteries, smoke detector, pull station and several duct smoke detectors tested ok today. Will need to finish testing of the remaining duct smoke detectors prior to a final. Will also need document box, map and knox box.
|
INSP-Final Inspection | 1/30/2015 | 2/2/2015 | 2/2/2015 | A | PEND |
Forrest France
|
|
|
Discussed plan modification and date reviewed, project schedule and RTU installations.
|
INSP-Final Inspection | 8/8/2014 | 8/8/2014 | 8/8/2014 | P | FAIL |
Troy Cobbley
|
|
|
Provide city approved data sheets and as-built drawings/complete submittals as dsicussed. Functional testing of system passed.
|