INSP-Final Inspection | 1/14/2016 | 1/15/2016 | 1/15/2016 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 1/13/2016 | 1/14/2016 | 1/14/2016 | P | FAIL |
Troy Cobbley
|
|
|
Need the as-built drawings as discussed and then the project can be finaled.
|
INSP-Final Inspection | 2/5/2015 | 2/6/2015 | 2/6/2015 | A | FAIL |
Troy Cobbley
|
|
|
Fire alarm testing complete. Need the non-functional hvac units repaired or removed. If repaired I need to finish testing. If removed I need revised drawings.
|
INSP-Final Inspection | 1/29/2015 | 1/30/2015 | 1/30/2015 | A | FAIL |
Troy Cobbley
|
|
|
Need plan modificatios and the hvac unit/shut down addressed.
|
INSP-Final Inspection | 1/29/2015 | 1/29/2015 | 1/29/2015 | A | FAIL |
Troy Cobbley
|
|
|
We were only able to test one duct smoke detector due to not being able to get the remaining hvac units to function. I noted that the smoke detectors for the fire door release do not appear to be installed per NFPA 80 and Chapter 17 of NFPA 72
|
INSP-Final Inspection | 1/29/2015 | 1/30/2015 | 1/29/2015 | A | CANC |
Troy Cobbley
|
|
|
Please notify Greg 30 min. prior to arrival. Thank you! Phone #: ###-#### >> Inspection requested via web by Stacie Tasker Inspection cancelled from web by: Stacie Tasker
|
INSP-Final Inspection | 1/27/2015 | 1/28/2015 | 1/28/2015 | A | FAIL |
Troy Cobbley
|
|
|
Resubmit plans for a "plan modification" for the additional flow switches, tamper switches and the cellular dialer. Provide auto-resetting tamper switches on the existing anti-freeze loop control valves, repair or remove the non-functional hvac units to facilitate the testing of the duct smoke detectors, remove or provide connection to the door mags.
|
INSP-Final Inspection | 8/8/2014 | 8/8/2014 | 8/8/2014 | P | FAIL |
Troy Cobbley
|
|
|
Provide city approved data sheets and as-builts/submittals as discussed. Functional testing of system passed.
|