Permit Information
Permit NumberFIR14-00581
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 1550 S CLOVERDALE RD
Project NameBOISE TECH MALL
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of protecting a three level building with above and below protection. The above protection utilizes concealed combustible sprinklers, spaced at a maximum of 14’x14’. Each floor is looped and has a floor level control valve. The branch lines are 1½” and the mains are 2”. The first two levels are designed as mercantile (Ordinary Hazard II). The top level is designed as office (Light Hazard)

To construct a new 11,860 square foot, three story, wood framed office and retail building and related site improvements. The sprinklers are used for substitution for one-hour fire-resistive construction. 1st FL: 3,900 sq. ft., 2nd FL: 3,995 sq. ft., 3rd FL: 3,965 sq. ft.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/11/201412/12/201412/12/2014APASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection12/9/201412/9/201412/9/2014PFAIL
DetailsTroy Cobbley
Could not final out inspection due to fire alarm problems. However the forward flush passed
INSP-Final Inspection12/5/201412/5/201412/5/2014PCANC
DetailsTroy Cobbley
Canceled per discussion with Jeff Packham
INSP-Sprinkler Rough-in10/24/201410/24/201410/24/2014PPASS
DetailsTroy Cobbley
The north and south stairwell insulation is complete and can be covered. The second floor insulation is complete and piping can be covered.
INSP-Sprinkler Rough-in/Hydro10/14/201410/14/201410/14/2014PPASS
DetailsTroy Cobbley
2nd & 3rd floor overhead hydro tests passed
INSP-Sprinkler Rough-in/Hydro10/9/201410/10/201410/10/2014APASS
DetailsTroy Cobbley
1st floor hydro test passed on the second try.
INSP-Sprinkler Rough-in10/8/201410/9/201410/9/2014APART
DetailsTroy Cobbley
Todays inspection was for a rough-in for the second and third floors. Rough-in passed. Two locations are marked where heads have not been installed yet. Third floor piping is ok to cover. First, second and the stairwells can not be covered until insulation/filling has been verified.
INSP-Sprinkler Rough-in9/10/20149/11/20149/11/2014APASS
DetailsTroy Cobbley
Inspection was for the first floor only. With the removal of the upright heads the installation matches the revised plans. Tim is ok with the revised piping in the first floor. Piping can not be covered until the installation of the insulation has been approved.
INSP-Sprinkler Rough-in8/28/20148/29/20148/29/2014APART
DetailsTroy Cobbley
Inspection turned into a conference. I noted, and we discussed, the extensive amount of obstructions caused by mechanical duct work. It does not appear that any of the obstruction rules for the CC heads can be met and that additional sprinkler heads will be required. With additional heads hydraulic calculations/pipe routing will/could be effected and plan modifications required. I also noted that the area under the stairs is combustible and does not have sprinkler protection. This will require special consideration to meet NFPA 13 requirements prior to a cover inspection.