INSP-Final Inspection | 6/22/2015 | 6/22/2015 | 6/22/2015 | P | PASS |
Thomas Walsh
|
|
|
Final Inspection - PASSED
|
INSP-Sprinkler Rough-in/Hydro | 6/22/2015 | 6/22/2015 | 6/22/2015 | P | PASS |
Thomas Walsh
|
|
|
Retested one HVAC unit for SD shutdown for the Bldg. D commons area. The unit shutdown when tested. That was the last test needed for final sign-off. PASSED and Finaled.
|
INSP-Final Inspection | 6/12/2015 | 6/12/2015 | 6/12/2015 | A | FAIL |
Thomas Walsh
|
|
|
Final inspection of fire alarm system for Bldg D and common areas. One HVAC duct detector is not shutting down its assoc, HVAC unit. Three other units tested OK.
|
INSP-Alarm Testing | 6/9/2015 | 6/10/2015 | 6/10/2015 | P | PART |
Thomas Walsh
|
|
|
Fire alarm system testing for Bldg. D commons area, including MP, SDs, CO detectors, heat detectors. One H/S unit in the kitchen area is not silencing properly. No FSDs. or elevators tested this visit.
|
INSP-Alarm Testing | 6/8/2015 | 6/8/2015 | 6/8/2015 | P | PART |
Thomas Walsh
|
|
|
Inspection/ test of fire alarm system for the permit coverage area, except common area of Bldg D., including manual pulls, smoke detection, waterflows, tamper supervisories, and audibility/visual device testing. All addresses appeared to be accurate. NOTE: No FSDs or elevator functions tested this visit.
|