INSP-Final Inspection | 1/29/2015 | 1/30/2015 | 1/30/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 1/28/2015 | 1/29/2015 | 1/29/2015 | A | FAIL |
Troy Cobbley
|
|
|
Outside alarm bell did not ring upon activation of the dry pipe system.
|
INSP-Sprinkler Rough-in/Hydro | 1/20/2015 | 1/21/2015 | 1/21/2015 | P | PASS |
Troy Cobbley
|
|
|
24 hr air test passed
|
INSP-Sprinkler Rough-in/Hydro | 1/20/2015 | 1/20/2015 | 1/20/2015 | P | PART |
Troy Cobbley
|
|
|
Rick-24 hr air test started at 10:00am with 40 psi on the guage
|
INSP-Sprinkler Rough-in/Hydro | 1/15/2015 | 1/16/2015 | 1/16/2015 | A | PASS |
Troy Cobbley
|
|
|
Overhead 200lb hydro for both the wet and dry systems passed.
|
INSP-Sprinkler Rough-in | 1/14/2015 | 1/15/2015 | 1/15/2015 | A | PASS |
Troy Cobbley
|
|
|
Piping in office area can be covered. 6" main installed and passed. Heads under doors installed and passed
|
INSP-Sprinkler Rough-in | 12/29/2014 | 12/30/2014 | 12/30/2014 | A | PASS |
Troy Cobbley
|
|
|
6" main needs to be installed/inspected and the tie-in's to the existing system. Outside canopy is ok to cover. Need sprinkler coverage installed under doors.
|
INSP-Sprinkler Rough-in | 12/19/2014 | 12/19/2014 | 12/19/2014 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler piping above the restrooms is ok to cover.
|
INSP-Sprinkler Rough-in | 10/29/2014 | 10/29/2014 | 10/29/2014 | P | PASS |
Troy Cobbley
|
|
|
The 5'-0" stub out is ok to bury.
|