Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR14-00745
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 222 S AUTO DR
Project NameLARRY H MILLER COLL. REP. CNTR
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of a one new dry and one new wet system to protect a new addition. The dry system is protecting a drive in canopy. The wet system protects the remainder of the new addition. The 6” underground supplies a 6” backflow preventer, 6” wet system riser and 3” wet system riser.

The underground is under permit FIR14-00596

Per the designer there is no flammable liquid spraying in the permitted scope of work. There is a large opening adjoining the paint department expansion. The designer indicated there was no flammable liquid spraying in this adjoining area.

Larry H. Miller - Body Shop and Office Addition - To demolish and remove an approximate 7,000 sq. ft., two story office area on the northeast corner of the building and construct a 21,035 sq. ft. office and repair garage addition, with a 2,035 sq. ft. storage mezzanine on the north end of an existing auto collision repair building. The existing showroom and repair shop on the south are unchanged and are separated from the north portion of the building by a four-hour firewall. This permit also includes related site improvements. This building is fully fire sprinklered. The sprinklers are used for area increase. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/29/20151/30/20151/30/2015APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection1/28/20151/29/20151/29/2015AFAIL
DetailsTroy Cobbley
Outside alarm bell did not ring upon activation of the dry pipe system.
INSP-Sprinkler Rough-in/Hydro1/20/20151/21/20151/21/2015PPASS
DetailsTroy Cobbley
24 hr air test passed
INSP-Sprinkler Rough-in/Hydro1/20/20151/20/20151/20/2015PPART
DetailsTroy Cobbley
Rick-24 hr air test started at 10:00am with 40 psi on the guage
INSP-Sprinkler Rough-in/Hydro1/15/20151/16/20151/16/2015APASS
DetailsTroy Cobbley
Overhead 200lb hydro for both the wet and dry systems passed.
INSP-Sprinkler Rough-in1/14/20151/15/20151/15/2015APASS
DetailsTroy Cobbley
Piping in office area can be covered. 6" main installed and passed. Heads under doors installed and passed
INSP-Sprinkler Rough-in12/29/201412/30/201412/30/2014APASS
DetailsTroy Cobbley
6" main needs to be installed/inspected and the tie-in's to the existing system. Outside canopy is ok to cover. Need sprinkler coverage installed under doors.
INSP-Sprinkler Rough-in12/19/201412/19/201412/19/2014PPASS
DetailsTroy Cobbley
Sprinkler piping above the restrooms is ok to cover.
INSP-Sprinkler Rough-in10/29/201410/29/201410/29/2014PPASS
DetailsTroy Cobbley
The 5'-0" stub out is ok to bury.