INSP-Final Inspection | 8/20/2015 | 8/21/2015 | 8/21/2015 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Final Inspection | 8/14/2015 | 8/14/2015 | 8/14/2015 | P | CANC |
Jim Page
|
|
|
Spoke with POC over the phone, Mike Phone #: ###-####, Simplex still needs to install pull stations for foam system avtivation, cannot final until pulls stations are installed and tested for actuation.
|
INSP-Sprinkler Rough-in | 8/12/2015 | 8/12/2015 | 8/12/2015 | P | PASS |
Troy Cobbley
|
|
|
Todays inspection was for flow verification of the foam system. This verification failed. See the plan reviewer attached notes on the specificsof what was witnessed
______________________________________
Below add by Plan Reviewer TRF
Based on the following the foam test PASSED.
NFPA 409 6.1.1 (3)
NFPA 409 6.2.5.3 (withing 5' in 3 minutes)
NFPA 409 6.2.5.5.1 (local application, NFPA 11)
NFPA 11 6.13.3.3.1 (2 ft within 2 min)
The requiment of 2' of foam was met in 1:50 seconds.
|
INSP-Sprinkler Rough-in | 8/11/2015 | 8/11/2015 | 8/11/2015 | P | DONE |
Troy Cobbley
|
|
|
Boise Fire Dept. witnessed the flowing water at the foam generators. Forrest France verified required pressure at foam generator.
|
INSP-Sprinkler Rough-in/Hydro | 8/6/2015 | 8/7/2015 | 8/7/2015 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro tests of the four foam systems (DDX valves) passed.
|
INSP-Supply line flush | 8/5/2015 | 8/6/2015 | 8/6/2015 | A | CANC |
Troy Cobbley
|
|
|
Mike Phone #: ###-####
|
INSP-Conference | 8/4/2015 | 8/5/2015 | 8/5/2015 | A | DONE |
Troy Cobbley
|
|
|
Todays inspection was for certification of the 3 fire pumps. Inspection passed. We found that all three pumps are 3psi to 7psi above on Churn. Both diesel pumps are 4psi to 5psi low at 150%. After conferencing with Tim Frost and Gary with Tolco pumps that this is still acceptable. We actually moved the guages and gained acouple of psi.
|
INSP-Sprinkler Rough-in | 6/30/2015 | 7/1/2015 | 7/1/2015 | A | PASS |
Troy Cobbley
|
|
|
The remaining underground supply piping for the test header is ok for cover. Ball drip has been installed in vault.
|
INSP-Sprinkler Rough-in/Hydro | 6/24/2015 | 6/24/2015 | 6/24/2015 | P | PASS |
Troy Cobbley
|
|
|
Todays inspection was for the hanger area. Rough-in passed. Mike is going to provide verifircation that the two tech screws used for the 2" branchline hanger is approved. I need to verify that hanger clips are not required (data sheet provided with submittal)
|
INSP-Sprinkler Rough-in/Hydro | 6/15/2015 | 6/15/2015 | 6/15/2015 | P | PASS |
Jim Page
|
|
|
Hydrostatic test complete on the three wet systems
|
INSP-Sprinkler Rough-in | 6/5/2015 | 6/5/2015 | 6/5/2015 | P | PASS |
Katie Marron
|
|
|
Rough-in of grid ceiling areas OK to cover. One sprinkler head overspaced in front office (south west of main door). Needs to be adjusted left to the adjacent 2x2 grid per drawing..
|
INSP-Sprinkler Rough-in | 5/7/2015 | 5/8/2015 | 5/8/2015 | A | PART |
Katie Marron
|
|
|
Rough-in inspection for office area wet system. Ok to cover hard lid and grid ceiling areas. Notice items: aux. drain missing, flex drops for grid ceiling to be finalized and possible missed coverage/HVAC obstruction in mechanical bay.
|