INSP-Final Inspection | 3/26/2015 | 3/27/2015 | 3/27/2015 | A | PASS |
Forrest France
|
|
|
Completed dry system trip test, riser supervision, final walkthrough and verification of noted correction items.
|
INSP-Sprinkler Rough-in | 2/18/2015 | 2/19/2015 | 2/19/2015 | A | PART |
Forrest France
|
|
|
Regarding coverage at the exit corridor.
|
INSP-Sprinkler Rough-in/Hydro | 2/10/2015 | 2/11/2015 | 2/12/2015 | P | PART |
Forrest France
|
|
|
Concluded satisfactory pneumatic test of the dry system with no pressure loss at the guage.
|
INSP-Sprinkler Rough-in | 2/10/2015 | 2/10/2015 | 2/10/2015 | P | PART |
Forrest France
|
|
|
Begin 24 hr air test of the dry system at 1:30PM @ 40psig.
|
INSP-Sprinkler Rough-in/Hydro | 1/22/2015 | 1/23/2015 | 1/23/2015 | A | PART |
Forrest France
|
|
|
Hydrostatic testing of the new dry system piping passed. Also verified completion of previous C/N items including added coverage at the vestibule, flex couplings at the main, adjusted spacing, outside WF bell installed.
|
INSP-Sprinkler Rough-in | 1/22/2015 | 1/23/2015 | 1/23/2015 | A | PART |
Forrest France
|
|
|
Completed satisfactory hydrostatic test of the new dry system.
|
INSP-Sprinkler Rough-in | 1/16/2015 | 1/16/2015 | 1/16/2015 | A | PART |
Forrest France
|
|
|
Completed rough-in inspection of the new dry system at the 2nd floor parking garage- items noted include; overspacing between two branchlines west end, missing coverage at the vestibule, provide flexible couplings at riser main between floors, missing forward flow provision at the riser, new outside WF bell needed, revise existing FDC signage.
|
INSP-Sprinkler Rough-in | 1/8/2015 | 1/12/2015 | 1/12/2015 | A | PART |
Forrest France
|
|
|
|