INSP-Final Inspection | 5/21/2015 | 5/22/2015 | 5/22/2015 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 5/19/2015 | 5/20/2015 | 5/20/2015 | A | CANC |
Troy Cobbley
|
|
|
Project related fire alarm permit not called in for inspection.
|
INSP-Final Inspection | 5/18/2015 | 5/19/2015 | 5/19/2015 | A | FAIL |
Troy Cobbley
|
|
|
1.No pressure relief valve installed. 2. Backflow assembly neededs to be tested by certified backflow tester. 3. Forward flush needs to be performed. 4. No ball drip on FDC. 5. Fire alarm needs to be retested.
|
INSP-Final Inspection | 5/13/2015 | 5/14/2015 | 5/14/2015 | A | FAIL |
Troy Cobbley
|
|
|
No inspection was performed due to the fire alarm monitoring system not being complete. Also the tamper switch for the PIV has not been installed.
|
INSP-Sprinkler Rough-in/Hydro | 3/24/2015 | 3/25/2015 | 3/25/2015 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro and rough-in passed
|
INSP-Sprinkler Rough-in/Hydro | 2/11/2015 | 2/11/2015 | 2/11/2015 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed.
|