INSP-Final Inspection | 4/30/2015 | 5/1/2015 | 5/1/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 4/23/2015 | 4/24/2015 | 4/24/2015 | A | CANC |
Troy Cobbley
|
|
|
Canceled due to fire alarm panel not being functional yet.
|
INSP-Sprinkler Rough-in/Hydro | 4/22/2015 | 4/22/2015 | 4/22/2015 | P | PART |
Troy Cobbley
|
|
|
Overhead hydro test passed. Rough-in passed for the most part. Missing two longitudinal braces on the 1 1/2" main and two branch line restraints under the mezzanine. Need updated/approved plans showing the pipe sizing and pipe routing changes under the mezzanine prior to a final sign off.
|
INSP-Supply line flush | 4/16/2015 | 4/17/2015 | 4/17/2015 | A | PASS |
Troy Cobbley
|
|
|
Underground flush of the remote FDC and the underground supply passed
|
INSP-Sprinkler Rough-in/Hydro | 4/15/2015 | 4/16/2015 | 4/16/2015 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line and remote FDC hydro tests passed
|
INSP-Sprinkler Rough-in | 4/10/2015 | 4/10/2015 | 4/13/2015 | P | PASS |
Troy Cobbley
|
|
|
Remaining underground ok to cover
|
INSP-Sprinkler Rough-in | 4/8/2015 | 4/9/2015 | 4/9/2015 | P | PART |
Troy Cobbley
|
|
|
Supply line rough-in passed. Just missing thrust blocks and one fitting on the remote FDC. Vault also needs to be installed prior to cover.
|