INSP-Final Inspection | 9/23/2015 | 9/24/2015 | 9/24/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Alarm Testing | 6/15/2015 | 6/16/2015 | 6/16/2015 | A | DONE |
Troy Cobbley
|
|
|
Todays inspection was for the hvac shut down of the units on the second floor.
|
INSP-Alarm Testing | 6/9/2015 | 6/10/2015 | 6/10/2015 | P | DONE |
Troy Cobbley
|
|
|
Todays testing was for the hvac shut down on the first floor only. See the city approved plans for locations marked ok. Will need to test the detector over the security desk and the dampers/separation between floors when installed.
|
INSP-Sprinkler Rough-in | 6/1/2015 | 6/2/2015 | 6/2/2015 | A | PART |
Troy Cobbley
|
|
|
This inspection should have been scheduled as a final. A temporary occupancy is being given until the hvac shutdown, door mags and 3rd floor is complete.
|
INSP-Alarm Testing | 5/29/2015 | 6/1/2015 | 6/1/2015 | A | DONE |
Troy Cobbley
|
|
|
Water flow pressure switch has been corrected. Low air needs to be re-programmed. Need two door mag locks addressed as discussed. Tamper switches have been adjusted.
|
INSP-Alarm Testing | 5/26/2015 | 5/27/2015 | 5/27/2015 | P | DONE |
Troy Cobbley
|
|
|
Todays inspection we verified the Faast detection system (problems with low air and water flow), and verified the devices in the Warehouse. I noted that door mags are being used for security and will need to be addressed with the appropriate Fire Code and NFPA requirements.
|
INSP-Final Inspection | 5/22/2015 | 5/27/2015 | 5/27/2015 | A | CANC |
Troy Cobbley
|
|
|
Duplicate inspection
|
INSP-Final Inspection | 5/22/2015 | 5/26/2015 | 5/26/2015 | A | FAIL |
Troy Cobbley
|
|
|
Fire alarm testing for the first and second floors is complete. Correction previously noted have been address. Need HVAC issues addressed on all floors and the third floor fire alarm work completed.
|
INSP-Final Inspection | 5/22/2015 | 5/22/2015 | 5/22/2015 | P | FAIL |
Troy Cobbley
|
|
|
First floor corrections complete, second floor audio/visuals passed. Still need outside alarm bell repaired and heat detectors in elevator shafts tested. HVAC still needs to be addressed
|
INSP-Alarm Testing | 5/20/2015 | 5/21/2015 | 5/21/2015 | A | DONE |
Troy Cobbley
|
|
|
See the city approved plans for locations and devices tested which included the elevator recall. Elevator fire doors need to be adjusted/repaired, PIV needs adjusted and the outside alarm bell did not function.
|
INSP-Alarm Testing | 5/19/2015 | 5/20/2015 | 5/20/2015 | A | CANC |
Troy Cobbley
|
|
|
Ken and I agreed to reshedule for tomorrow morning at 7:00am
|
INSP-Alarm Testing | 5/18/2015 | 5/19/2015 | 5/19/2015 | A | DONE |
Troy Cobbley
|
|
|
Todays inspection verified the FACP and the NAC panel. Also verified tamper switches as marked on the city approved plans. Also verifed placement and function of the first floor NAC circuits/devices. I noted several overspaced strobes as marked on the plans. I spoke to the general contractor about duct smoke detectors (he is waiting on an RFI)
|