INSP-Final Inspection | 4/29/2015 | 4/30/2015 | 4/29/2015 | A | PASS |
Katie Marron
|
|
|
Inspection completed on 4/29/15. Scope of work complete. Verified all heads are now standard response 200 degree. Permit finaled.
|
INSP-Final Inspection | 4/20/2015 | 4/21/2015 | 4/21/2015 | A | CANC |
Katie Marron
|
|
|
Robert is your contact on site. Please call 1/2 hour prior to inspection. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Final Inspection | 4/20/2015 | 4/22/2015 | 4/21/2015 | P | CANC |
Troy Cobbley
|
|
|
Robert is your contact on site. Please call 1/2 hour prior to inspection. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 4/17/2015 | 4/20/2015 | 4/20/2015 | P | FAIL |
Katie Marron
|
|
|
Mixed response heads; new are quick, existing are standard. Replace so heads match response and temperature.
|
INSP-Sprinkler Rough-in | 3/16/2015 | 3/17/2015 | 3/17/2015 | A | FAIL |
Forrest France
|
|
|
Items noted include; mixed temp heads, plans indicate 200 deg. heads to be installed, overspaced coverage, field work completed exceeds scope of permit work shown on approved plans- additional heads have been added, coverage below stairs provided and a new riser manifold with control valves added. Need to resubmit plans matching work completed.
|