INSP-Final Inspection | 9/21/2015 | 9/22/2015 | 9/22/2015 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete per Troy Cobbley
|
INSP-Final Inspection | 9/1/2015 | 9/2/2015 | 9/2/2015 | A | FAIL |
Troy Cobbley
|
|
|
Provide listed air maintenance device, provide pipe size changes in the "dog houses".
|
INSP-Alarm Testing | 7/14/2015 | 7/15/2015 | 7/15/2015 | A | CANC |
Troy Cobbley
|
|
|
Duplicate inspection
|
INSP-Alarm Testing | 7/13/2015 | 7/14/2015 | 7/14/2015 | P | PASS |
Troy Cobbley
|
|
|
24 hr air test Boise Spectrum - Bldg C passed
|
INSP-Alarm Testing | 7/13/2015 | 7/13/2015 | 7/14/2015 | P | PASS |
Troy Cobbley
|
|
|
24 hr air test Boise Spectrum - Bldg C started with guage pressure marked.
|
INSP-Sprinkler Rough-in/Hydro | 7/8/2015 | 7/10/2015 | 7/10/2015 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|