INSP-Final Inspection | 9/21/2015 | 9/22/2015 | 9/22/2015 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete per Troy Cobbley
|
INSP-Final Inspection | 9/18/2015 | 9/18/2015 | 9/18/2015 | P | CANC |
Troy Cobbley
|
|
|
Please call 30 min prior to arrival.
Thank you, Phone #: ###-#### >> Inspection requested via web by Scott Carter II Inspection cancelled from web by: Scott Carter II
|
INSP-Final Inspection | 9/1/2015 | 9/2/2015 | 9/2/2015 | A | FAIL |
Troy Cobbley
|
|
|
The air maintenance device does not appear to be listed. Replace or provide verification.
|
INSP-Alarm Testing | 7/14/2015 | 7/15/2015 | 7/15/2015 | A | PASS |
Troy Cobbley
|
|
|
24 hr air test Boise Spectrum - Bldg B passed
|
INSP-Alarm Testing | 7/13/2015 | 7/14/2015 | 7/14/2015 | P | PART |
Troy Cobbley
|
|
|
24 hr air test Boise Spectrum - Bldg B started at 9:00am with pressure marked on guage
|
INSP-Alarm Testing | 7/13/2015 | 7/13/2015 | 7/14/2015 | P | FAIL |
Troy Cobbley
|
|
|
24 hr air test Boise Spectrum - Bldg B failed. Door was locked to riser room
|
INSP-Sprinkler Rough-in/Hydro | 7/8/2015 | 7/10/2015 | 7/10/2015 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|