Description
The fire sprinkler scope of work consists of adding, plugging and relocating sprinklers to accommodate new wall and ceiling configuration.

(IDAHO CENTRAL CREDIT UNION) The exterior work consists of installing new composite metal panels, installing new standing seam metal roof, replace existing glazing with new glazing to match existing glazing, paint exterior cmu, replace existing parking lot lighting, and rework the east parking lot and parking lot landscaping. Interior TI work consist of demolition of existing improvements including walls doors, windows, ceilings window sills, mechanical, electrical, lighting. New interior work shall include new walls doors, windows, ceilings window sills, mechanical, electrical, lighting and
fire sprinkler system rework. Additionally the TI will include the infilling of two existing opening in the first and second floor atrium. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department.**ajs**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/10/201512/10/201512/10/2015PPASS
DetailsJim Page
Final fire sprinkler inspection passed/complete
INSP-Final Inspection12/7/201512/7/201512/7/2015PCANC
DetailsJim Page
Spoke to Brian with Absolute, inspection will be rescheduled for 08DEC2015.
INSP-Sprinkler Rough-in11/13/201511/13/201511/13/2015PPASS
DetailsJim Page
Rough to cover inspection passed/complete for 2nd floor, entire floor approved for cover.
INSP-Sprinkler Rough-in11/5/201511/9/201511/9/2015APART
DetailsJim Page
Rough to cover inspection passed/complete for basement level work, first floor work and exterior office spaces on 2nd floor. These mentioned area's approved for cover. Contractor will schedule rough to cover for remaining area's of 2nd floor when complete.