INSP-Final Inspection | 8/24/2015 | 8/24/2015 | 8/24/2015 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 8/22/2015 | 8/22/2015 | 8/22/2015 | P | PASS |
Thomas Walsh
|
|
|
Hydrotest of FS U/G supply line from city connection to A/S BOR - 200 psi @ hours - PASSED. Waterflow device tested OK Contractor still in process of sheet rocking areas where sprinklers protrude through ceiling. Also need to install ceiling in electrical closet. Need to install 4-way siesmic brace at top of riser. Will inspect these discrepancies at final inspection.
|
INSP-Sprinkler Rough-in/Hydro | 8/21/2015 | 8/21/2015 | 8/21/2015 | P | PART |
Thomas Walsh
|
|
|
Flush test of FS U/G supply line from city connection to A/S BOR (before connection to A/S system. Flushed clear after 2 attempts. OK to connect to A/S BOR.
|
INSP-Supply line flush | 8/20/2015 | 8/21/2015 | 8/21/2015 | P | PART |
Thomas Walsh
|
|
|
Witnessed hydrostatic test of above ground system (200 psi @ 2 ours) - PASSED NOTE: FS U/G supply line installed but not hydrotested yet - scheduled for tomorrow 8/22. Following hydro and flush, connection to A/G system will be made and the system put into service.
|
INSP-Sprinkler Rough-in/Hydro | 8/20/2015 | 8/21/2015 | 8/21/2015 | A | PART |
Thomas Walsh
|
|
|
Started hydrotest @ 1045 - 200 psi. Rough inspection conducted 8/20.
|
INSP-Sprinkler Rough-in | 8/19/2015 | 8/20/2015 | 8/20/2015 | A | PASS |
Troy Cobbley
|
|
|
The overhead rough-in passed and piping can be covered except at the wall where the insulation needs to be installed in the stud bays and at the locations for the missing branch line restraints. No riser has been installed/built. Underground supply has not been connected at the street yet.
|
INSP-Sprinkler Rough-in | 8/17/2015 | 8/18/2015 | 8/18/2015 | A | PASS |
Troy Cobbley
|
|
|
The remaining underground has been installed by tunneling. I need documentation verifying that the minimum 4'6" bury depth has been met. I was able to verify depth at the point of connection to tvfp piping.
|
INSP-Sprinkler Rough-in | 8/11/2015 | 8/12/2015 | 8/12/2015 | A | PASS |
Troy Cobbley
|
|
|
Underground supply stub out only ok to cover.
|