INSP-Final Inspection | 8/25/2015 | 8/25/2015 | 8/25/2015 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. system is on line
|
INSP-Final Inspection | 8/24/2015 | 8/25/2015 | 8/24/2015 | A | PASS |
Scott Arellano
|
|
|
Passed
|
INSP-Final Inspection | 8/20/2015 | 8/21/2015 | 8/21/2015 | P | PART |
Thomas Walsh
|
|
|
Fire alarm system test for a new charter school. Tested all initiating devices, including SDs, DDs, MP,s tamper, etc, and notification throughout the building. All devices tested OK. Offsite monitoring confimed, however system will not be put into service until the fire sprinkler system is ready to be put into service.
|