Description
[George's Cycle]
The fire sprinkler scope of work consists of protecting a two level building. Both levels are protected with a grid type layout.

(GEORGE'S CYCLE)MECHANICAL IS A DEFERRED SUBMITTAL. Conversion of an existing auto parts warehouse and retail building into a bicycle retail shop and warehouse. This is a partial change of occupancy 15,611 sq ft on the main level and 7,735 sq ft of existing basement storage. . The Work to include exterior modifications as shown on approved plans. New opening cut in existing slab to relocate the stairs from the basement to meet the required separation, new accessible route, new nonbearing interior partition walls. This building will have a fire sprinkler system installed as part of this project to remove the existing firewall. The site work taking place in within ACHD right of way. The mechanical design and equipment is a deferred submittal. . This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **ajs**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/11/201512/11/201512/11/2015PPASS
DetailsJim Page
All previously noted items repaired. Final fire sprinkler inspection passed/complete.
INSP-Final Inspection12/8/201512/9/201512/9/2015PCANC
DetailsJim Page
Contractor not ready for final inspection, previously noted items on last inspection still need to be addressed. Inspection cancelled per conversation with point of contact, Perly phone number ###-####, will reschedule for later date.
INSP-Final Inspection12/7/201512/8/201512/8/2015AFAIL
DetailsJim Page
No fire sprinkler head under overhead door, east side of tenant space. Overspacing of upright heads by new stairs install for main entry. Spacing issue with upright head by riser.
INSP-Sprinkler Rough-in/Hydro11/30/201511/30/201511/30/2015PPASS
DetailsJim Page
200 psi hydrostatic test for underground passed/complete
INSP-Sprinkler Rough-in/Hydro11/20/201511/20/201511/20/2015PFAIL
DetailsJim Page
200 psi hydrostatic test performed on the underground supply, underground lost @16psi during the 2 hour hydrostatic test. Underground will have to retested.
INSP-Sprinkler Rough-in/Hydro11/20/201511/20/201511/20/2015PPASS
DetailsJim Page
200 psi hydrostatic test passed/complete for the 2 overhead wet systems.
INSP-Supply line flush11/18/201511/19/201511/19/2015ADONE
DetailsJim Page
Underground flush for fire sprinkler main pssed/complete
INSP-Supply line flush11/9/201511/13/201511/12/2015ACANC
DetailsJim Page
UG Flush
Please call Perly 30 min prior ###-#### Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Scott Carter II
INSP-Sprinkler Rough-in10/14/201510/15/201510/15/2015APASS
DetailsJim Page
Underground rough-to cover inspection passed/complete, approved for cover
INSP-Sprinkler Rough-in10/2/201510/2/201510/2/2015PPASS
DetailsJim Page
Rough to cover inspection for hard lids on first floor passed/complete, approved to cover first floor hard lids.
INSP-Sprinkler Rough-in10/1/201510/1/201510/1/2015PFAIL
DetailsJim Page
Contractor requested inspection for rough to cover inspection on the hard lids, no hard lids approved for cover until upright head coverage is adjusted/corrected, multiple pockets above hard lids not covered and upright heads overspaced.