Permit NumberFIR15-00656
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 800 N MAPLE GROVE RD
Project Name#800 Ashville Commons 4-Plex
Customer Number 
ePlanReviewYes
Description
[Ashville Commons 4-Plex - #800]
The fire sprinkler scope of work consists of CPVC piping is being used with extended coverage residential sprinklers to protect a two level, four unit apartment building using NFPA 13R

The underground piping is under permit FIR15-00535

Bldg N (14) -Type 3 (Elev 3, A-203): To construct a new 3,804 sq. ft., two story, Four unit, apartment building. Each unit has two bedrooms, two bathrooms, and 951 square feet. The 1st story units are required to be Type 'B' units. All units share a common path of egress into and through a 1/2-hour rated exit corridor with 20 minute fire-resistive, listed, labeled, self-closing door assemblies from the dwelling units into the corridor. All construction per the approved plans, attached plan review report, and all other reviewing agencies approvals. One hour fire-partitions and one hour horizontal assemblies are required between dwelling units. This building is required to be fire sprinklered. The fire sprinkler system shall be per NFPA 13R as regulated by the fire department. DRH13-00300 & PUD12-00012 Per Planning and Zoning. **SRZ*
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/8/201512/10/201512/10/2015APASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in/Hydro10/6/201510/7/201510/7/2015APASS
DetailsTroy Cobbley
Overhead hydro test and tenting inspection passed. Piping can be covered.
INSP-Sprinkler Rough-in/Hydro10/5/201510/6/201510/6/2015PCANC
DetailsTroy Cobbley
Not ready for hydro test
INSP-Supply line flush10/2/201510/5/201510/5/2015APASS
DetailsTroy Cobbley
Underground flush passed
INSP-Sprinkler Rough-in/Hydro10/2/201510/5/201510/5/2015PPASS
DetailsTroy Cobbley
Rough-in passed. Piping can not be covered until a tenting inspection has passed.