INSP-Final Inspection | 3/8/2016 | 3/9/2016 | 3/9/2016 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 2/26/2016 | 2/29/2016 | 2/29/2016 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 2/25/2016 | 2/26/2016 | 2/26/2016 | A | FAIL |
Troy Cobbley
|
|
|
Overhead hydro failed due to visible loss at guage.
|
INSP-Sprinkler Rough-in/Hydro | 2/24/2016 | 2/25/2016 | 2/25/2016 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Supply line flush | 2/24/2016 | 2/25/2016 | 2/25/2016 | A | PASS |
Troy Cobbley
|
|
|
Supply line flush passed
|
INSP-Supply line flush | 2/10/2016 | 2/11/2016 | 2/11/2016 | A | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
|
INSP-Sprinkler Rough-in | 1/14/2016 | 1/14/2016 | 1/14/2016 | P | PASS |
Troy Cobbley
|
|
|
Rough-in and tenting passed. Piping can be covered.
|
INSP-Sprinkler Rough-in | 12/23/2015 | 12/23/2015 | 12/23/2015 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for the underground supply line passed/complete, approved for cover.
|