Permit Information
Permit NumberFIR15-00727
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 777 W MAIN ST
Project NameCity Center Plaza - District
Customer Number 
ePlanReviewYes
Description
[City Center Plaza - District Convention Center - Shell Protection & Standpipes]
The fire sprinkler scope of work consists of protecting a five level convention center. This five level project is considered a part of one large building consisting of this area, a nine story office, a five story office and an existing nineteen story bank. This project is for shell and core only and four manual wet standpipes.

Plan Mod #1
Tenant improvement. Minor additional ceilings except for top floor which was redesigned.

Plan Mod #2 – 9/16/2016
• FP-2: The hose valves shown on the roof have been relocated to the bottom of the alternating tread device that goes to the roof.
• FP-4: The sprinklers shown in the elevator pits have been removed from the convention center system. The sprinklers in the pits will be supplied from the existing US Bank building dry system as the pits reside within the area of the US Bank building.
• FP-4: An FDC has been added to the West side of the building within 300’ of a fire hydrant.
• FP-8: The standpipe supply has been revised to show the installed location of the supply on the North side of the building between columns 9 and 11.
• FP-9: (Added Sheet) A line has been added under a large duct that was installed as part of the tenant improvement. 5 sprinklers have been calculated to prove the line size used. This is a new remote area #10. Calculations also provided.

(CITY CENTER PLAZA) - Shell and Core Only - To complete the shell, core and exterior finishes for the 299,750 square foot, nine story office, retail, parking garage and convention center building with a 44,050 square foot, below grade bus transit center. PLAN MODIFICATION 9-3-15 – Modification submitted to modify structure and layout to accommodate finalized freight elevators and machine rooms.**TLW** This building is considered an addition to the existing approximate 304,610 square foot US Bank high rise building for allowable area, exterior opening and wall requirements. The existing high rise and new high rise addition will have separate sprinkler and alarm systems, as well as, their own fire command centers. This is a shell and core permit only and no occupancy is allowed under this permit. Separate tenant improvement permits will be required to finish this building for occupancy. All construction per the approved plans and attached comment list. JCM ***HIGH PRIORITY REVIEW***Contact Angie Brosious with any issues.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/15/201611/15/201611/15/2016APASS
DetailsJim Page
Pemit finaled
INSP-Final Inspection11/14/201611/14/201611/14/2016PPASS
DetailsJim Page
Final Fire Sprinkler Inspection complete.
INSP-Final Inspection10/31/201611/1/201611/1/2016APART
DetailsTroy Cobbley
Vertical sidewall heads have been added at the windows. I have had discussions with Scott about the requested final for this project and it has been determined that when the required signage is provided at all of the FDC's then a final on this permit can be given.
INSP-Final Inspection10/31/201610/31/201610/31/2016PFAIL
DetailsTroy Cobbley
The two new window sprinklers are not installed as per the installation guide for distance below the window mullion. Also before a final sign off the signage the describes the area serviced by the FDC's need to be installed. Scott and I discussed final sign offs.
INSP-Final Inspection9/20/20169/21/20169/21/2016APART
DetailsJim Page
Partial final for convention center fire sprinkler systems, area's complete are level 5, level 4, level 2 and level 1 lobby. Dry systems for level 3 and level 2 complete and in service. Level 1 fire sprinkler system will be inspected (excluding level 1 elevator lobby, sprinklers for this area complete)
INSP-Final Inspection9/13/20169/20/20169/20/2016PCANC
DetailsJim Page
Inspection request will be completed on 21SEPT2016, this inspection request cancelled and new inspection request coordinated with job site foreman.
INSP-Final Inspection9/19/20169/19/20169/19/2016PPART
DetailsJim Page
Partial final inspection complete for fire sprinklers, levels 4, 5 and 2 wet systems, complete for tampers, flow switch and final overhead fire sprinkler inspection. Level 3 dry system inspection complete, 2nd floor dry system will be completed at a later date.
INSP-Sprinkler Rough-in/Hydro9/13/20169/19/20169/19/2016PCANC
DetailsJim Page
No inspection request needed for today per conversation with Mike, phone number ###-####, this inspection request is cancelled.
INSP-Sprinkler Rough-in/Hydro9/16/20169/16/20169/16/2016PPASS
DetailsJim Page
Hydrostatic test complete for wet pipe? fire sprinkler systems located on levels 2 and 4 (Area labeled level 5 is off of the level 4 wet system) Standpipe hydrostatic test for district/convention center complete.
INSP-Sprinkler Rough-in9/9/20169/16/20169/16/2016PPASS
DetailsJim Page
24 hour air test complete for level 2 and level 3 dry systems protecting parking garages. 200psi hydrostatic test complete for parking garage dry systems (level 2 and 3)
INSP-Sprinkler Rough-in9/9/20169/15/20169/15/2016PPASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located in the soffits and above ceiling grid area's on level 2 of the convention center complete, overhead fire sprinkler piping located above soffits and ceiling grid area's on level 2 approved for cover.
INSP-Sprinkler Rough-in9/9/20169/14/20169/14/2016PCANC
DetailsJim Page
Inspection request for VRT, FIR16-00265. This inspection request cancelled and a new inspection request will be generated.
INSP-Sprinkler Rough-in9/9/20169/13/20169/13/2016PCANC
DetailsJim Page
Inspection request will be performed on 14SEPT2016.
INSP-Sprinkler Rough-in/Hydro9/13/20169/20/20169/13/2016PCANC
DetailsJim Page
Please schedule this final inspection for Convention Center. If you have questions please call Mike Martin at ###-####. Thank you. Phone #: ###-#### >> Inspection requested via web by Kay Haney Inspection cancelled from web by: Kay Haney
INSP-Sprinkler Rough-in9/9/20169/12/20169/12/2016PPASS
DetailsJim Page
Rough to cover inspection complete for overhead fire sprinkler piping located above the convention center level 2 soffits & hardlids, level 4 ceiling grid area's & hardlids, level 3 dry stsem as well as level 2 dry system, area's inspected for rough to cover inspection approved for cover.
INSP-Sprinkler Rough-in/Hydro9/9/20169/12/20169/9/2016PCANC
DetailsJim Page
Mike Martin is the contact for this inspection. He wanting a rough to cover inspection. Phone #: ###-#### >> Inspection requested via web by Kay Haney Inspection cancelled from web by: Kay Haney
INSP-Sprinkler Rough-in8/25/20168/25/20168/25/2016PPASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping in the ballroom, sections B and C complete. Overhead fire sprinkler piping located above the grid ceiling in ballroom approved for cover.
INSP-Sprinkler Rough-in8/23/20168/23/20168/23/2016PPASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located above the ceiling grid in ballroom Section A complete, overhead fire sprinkler in ballroom Section A approved for cover. Rough to cover inspection for overhead fire sprinkler piping located in level 4 escalator lobby complete, overhead fire sprinkler piping located above the hardlids on level 4 escalator lobby approved for cover.
INSP-Sprinkler Rough-in/Hydro8/16/20168/16/20168/16/2016PCANC
DetailsJim Page
Hydrostatic test will be reschedule for later date.
INSP-Sprinkler Rough-in/Hydro8/15/20168/15/20168/15/2016PPART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping above restrooms in the commercial kitchen area complete, overhead piping above restroom hardlids in commercial kitchen approved for cover. Rough to cover inspection for overhead fire sprinkler piping located above the soffits on level 4 complete, overhead fire sprinkler piping located above level 4 soffits approved for cover. Rough in inspections for level 1 wet system complete, level 3 wet system complete, level 2 dry system complete as well as stairwells.
INSP-Sprinkler Rough-in/Hydro8/11/20168/12/20168/11/2016PCANC
DetailsJim Page
Inspection request rescheduled by me for 15AUG2016 per conversation with point of contact, Mike phone ###-####.
INSP-Sprinkler Rough-in8/11/20168/12/20168/11/2016PCANC
DetailsJim Page
Inspection request rescheduled by me for 15AUG2016 per conversation with point of contact, Mike phone ###-####.
INSP-Final Inspection7/26/20167/27/20167/27/2016ACANC
DetailsJim Page
Inspection request cancelled per conversation with point of contact, Mike phone number ###-####.