INSP-Final Inspection | 9/20/2016 | 9/21/2016 | 9/21/2016 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection passed/complete.
|
INSP-Final Inspection | 9/15/2016 | 9/20/2016 | 9/20/2016 | A | CANC |
Jim Page
|
|
|
Inspection request was moved to this afternoon, due to scheduling issues for this afternoon this inspection request is cancelled and will be rescheduled for 10am on 21SEPT2016.
|
INSP-Alarm Testing | 6/22/2016 | 6/23/2016 | 6/23/2016 | A | DONE |
Jim Page
|
|
|
Alarm testing complete, all devices with the new fire alarm system has been tested. A 10% functionality test will be performed on the new fire alarm system after the old fire alarm system and components have been removed. Note that the 5th floor pre-action isolation valve has a visible leak on the valve (leaks in the fire sprinkler system has the potential to cause false alarms), leak needs to be repaired before fire alarm system will by signed off as complete,
|
INSP-Final Inspection | 6/14/2016 | 6/15/2016 | 6/15/2016 | A | PART |
Jim Page
|
|
|
Tested smokes and A/V's on level 7, level 6, level 5 and level 4, all devices tested properly. Tested elevator recall as well as elevator shunt trip, devices tested corectly. Tested HVAC unit shutdown for in-duct smoke detectors on level 2, all tested correctly. Items left to inspect, associated devices with fire sprinkler system and VESDA systems.
|
INSP-Final Inspection | 5/10/2016 | 5/11/2016 | 5/11/2016 | A | PART |
Jim Page
|
|
|
Project is being worked in phases, contractor is going floor by floor for partial inspection and a final alarm inspection for entire building at project completion. Inspected level 3 smoke detectors and pull stations, remaining detection on level 3 is VESDA systems which will be tested at a later date. Level 1 smoke detectors/duct detectors/pull stations spot checked, devices tested operated correctly. Level 1 inspection complete, partial completion for level 3, contractor will schedule inspection request when other area's are ready.
|
INSP-Final Inspection | 3/8/2016 | 3/9/2016 | 3/9/2016 | A | PART |
Jim Page
|
|
|
Project is being worked in phases, contractor is going floor by floor for partial inspection and a final alarm inspection for entire building at project completion. Inspected basement level alarm system install with device testing, basement level inspection is passed/complete, contractor will schedule remaining floors for later date.
|
INSP-Conference | 1/5/2016 | 1/6/2016 | 1/6/2016 | A | DONE |
Jim Page
|
|
|
Fire alarm conference complete.
|