INSP-Final Inspection | 3/24/2016 | 3/25/2016 | 3/25/2016 | A | PASS |
Jim Page
|
|
|
Underground final inspection complete
|
INSP-Sprinkler Rough-in/Hydro | 3/24/2016 | 3/25/2016 | 3/25/2016 | A | PASS |
Jim Page
|
|
|
Underground hydrostatic complete
|
INSP-Sprinkler Rough-in | 3/1/2016 | 3/1/2016 | 3/1/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection performed on 18NOV2015 for underground piping, underground was approved for cover at that inspection.
|
INSP-Supply line flush | 2/28/2016 | 2/29/2016 | 2/29/2016 | P | DONE |
Jim Page
|
|
|
Underground main line flush complete.
|
INSP-Sprinkler Rough-in/Hydro | 2/28/2016 | 2/29/2016 | 2/29/2016 | A | PASS |
Jim Page
|
|
|
Hydrostatic test, 2 hours @ 200 psi complete for underground supply.
|
INSP-Supply line flush | 2/24/2016 | 2/26/2016 | 2/26/2016 | P | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with Robert, phone number ###-####, will reschedule for later date.
|
INSP-Sprinkler Rough-in/Hydro | 2/24/2016 | 2/26/2016 | 2/26/2016 | A | PASS |
Jim Page
|
|
|
Underground main supply hydrostatic test complete.
|