INSP-Final Inspection | 4/21/2016 | 4/21/2016 | 4/21/2016 | P | PASS |
Jim Page
|
|
|
Final fire alarm inspection passed/complete
|
INSP-Final Inspection | 3/21/2016 | 3/21/2016 | 3/21/2016 | P | PART |
Jim Page
|
|
|
Final alarm testing complete for phase 2, contractor will schedule final inspection for phase 3 when complete.
|
INSP-Final Inspection | 3/16/2016 | 3/17/2016 | 3/17/2016 | A | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with point of contatct, Morgan Phone #: ###-####, contractor will reschedule inspection for later date.
|
INSP-Final Inspection | 1/7/2016 | 1/8/2016 | 1/8/2016 | A | PART |
Troy Cobbley
|
|
|
Todays inspection was just to verify that the visual devices sync'd in phase one which they did.
|
INSP-Final Inspection | 12/30/2015 | 12/30/2015 | 12/30/2015 | P | FAIL |
Jim Page
|
|
|
Verified spacing and placement of Audio/Visual devices. Area of inspection passed for device placement, strobes need to be syncronized together when strobes are in same area. Contractor will reschedule inspection when sync issue repaired.
|