INSP-Final Inspection | 3/24/2016 | 3/25/2016 | 3/25/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Sprinkler Rough-in | 3/24/2016 | 3/25/2016 | 3/25/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection complete, approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 3/24/2016 | 3/25/2016 | 3/25/2016 | A | PASS |
Jim Page
|
|
|
Overhead hydrostatic test complete, 24 hour air test complete
|
INSP-Sprinkler Rough-in | 2/29/2016 | 3/1/2016 | 3/1/2016 | P | FAIL |
Jim Page
|
|
|
End of line seismic bracing missing on northwest branchlines.
|
INSP-Supply line flush | 2/29/2016 | 3/1/2016 | 3/1/2016 | P | DONE |
Jim Page
|
|
|
Underground main supply line flush complete
|
INSP-Sprinkler Rough-in/Hydro | 2/24/2016 | 2/29/2016 | 2/29/2016 | A | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with Robert, phone number ###-####, contractor will reshcedule hydrostatic test when water is turned on.
|