INSP-Final Inspection | 6/6/2016 | 6/6/2016 | 6/6/2016 | P | PASS |
Jim Page
|
|
|
Hydrostatic test was completed before final inspection under this inspection request. Final fire sprinkler inspection passed/complete.
|
INSP-Sprinkler Rough-in | 5/2/2016 | 5/2/2016 | 5/2/2016 | P | DONE |
Katie Marron
|
|
|
Underground flush completed satisfactorily.
|
INSP-Sprinkler Rough-in | 1/5/2016 | 1/5/2016 | 1/5/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection complete, tenting inspection for overhead piping complete, rough in inspection complete, approved for cover.
|
INSP-Sprinkler Rough-in | 12/31/2015 | 12/31/2015 | 12/31/2015 | P | CANC |
Jim Page
|
|
|
Inspection request cancelled, contractor will schedule rough to cover inspection after tenting of the overhead fire sprinkler piping is complete.
|