Permit Information
Permit NumberFIR15-00907
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 7000 W VICTORY RD
Project NameCRITICAL SYSTEMS CANOPY
Customer Number 
ePlanReviewYes
Description
[Critical Systems Canopy]
The fire sprinkler scope of work consists of and addition to a warehouse. A new 4” dry tree system will be supplied from the existing wet grid.

Contractor’s Note:
The building permit has not been issued at this time. The building department may determine that changes are required to the building plans in order to meet code. The changes may affect the sprinkler system. The sprinkler contractor will be obligated to make all necessary changes that may be required. Therefore, if the sprinkler contractor chooses to proceed without an issued building permit, they will do so on their own cognizance. This note does not constitute an early start agreement.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/5/20165/6/20165/6/2016APASS
DetailsTroy Cobbley
Permit finaled. Annual inspection is being performed by Shilo Automatic Sprinkler. I noted that the existing backflow preventer is "surging" which is causing the flow switch to continually acivated.
INSP-Final Inspection5/2/20165/4/20165/4/2016ACANC
DetailsTroy Cobbley
Canceled due to fire alarm issues.
INSP-Conference4/20/20164/22/20164/22/2016APASS
DetailsTroy Cobbley
24 hour air test passed
INSP-Conference4/20/20164/21/20164/21/2016ADONE
DetailsTroy Cobbley
Air test started at 9:30. See pressure marked on guage.
INSP-Sprinkler Rough-in/Hydro4/19/20164/19/20164/19/2016PPASS
DetailsTroy Cobbley
Overhead hydro test (200psi) passed.
INSP-Sprinkler Rough-in3/30/20163/31/20163/31/2016APART
DetailsTroy Cobbley
Rough-in inspection mostly passed. Missing earthquake bracing. Missing flexible couplings at top of risers. Missing clearance at piping penatration into new building. Missing information on plans showing how long the sprig ups should be. Don't know if sprig ups and the way the riser nipples are installed are approved since they are not shown on the plans. Need verification from plan review. Need air maintenance device.