Information based on query as of Thursday, June 27, 2024.
Permit Information
Permit NumberFIR15-00912
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 2910 E AMITY RD
Project NameHayden Beverage Warehouse
Customer Number 
ePlanReviewYes
Description
[Hayden Beverage Warehouse]
The fire sprinkler scope of work consists of Phase I Fire Protection Upgrade, convert three existing systems to ESFR sprinklers. The 4 new system risers will be supplied by a new 10" fire service line to supply a new 1500 Gpm @ 90 Psi electric fire pump.

Contractor’s Note:
The building permit has not been issued at this time. The building department may determine that changes are required to the building plans in order to meet code. The changes may affect the sprinkler system. The sprinkler contractor will be obligated to make all necessary changes that may be required. Therefore, if the sprinkler contractor chooses to proceed without an issued building permit, they will do so on their own cognizance. This note does not constitute an early start agreement.

**Project Management-Ron Hill**(HAYDEN BEVERAGE - Loading Dock Addition) Phase I permit for exterior and interior improvements to an existing building with work to include partial removal exterior wall sections to accommodate new overhead doors and the construction of a new below grade loading dock approaches per the approved plans. This is a fully fire sprinklered building for unlimited area. Any alterations to the sprinkler system will require a separate permit and shall comply with NFPA 13 as regulated by the fire department. Phase 2 being done under separate permit of BLD15-04516. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/14/20163/15/20163/15/2016PPASS
DetailsJim Page
Phase 1 final fire sprinkler inspection passed/complete
INSP-Alarm Testing3/14/20163/15/20163/15/2016PDONE
DetailsJim Page
Alarm testing complete
INSP-Sprinkler Rough-in/Hydro3/14/20163/15/20163/15/2016APASS
DetailsJim Page
Hydrostatic test (200 psi for 2 hours) complete for the four wet systems in the fire pump room. Rough in inspection complete for phase 1 fire sprinkler piping.
INSP-Sprinkler Rough-in3/7/20163/10/20163/10/2016ADONE
DetailsJim Page
Fire pump flow/testing complete
INSP-Supply line flush2/10/20162/11/20162/11/2016APASS
DetailsJim Page
Underground fire line flush passed/complete.
INSP-Sprinkler Rough-in/Hydro2/10/20162/10/20162/10/2016PPASS
DetailsJim Page
Underground hydrostatic (200psi for 2 hours) test passed/complete.
INSP-Sprinkler Rough-in1/21/20161/21/20161/21/2016PPASS
DetailsJim Page
Rough to cover inspection for the underground passed/complete, underground approved for cover.
INSP-Sprinkler Rough-in1/19/20161/19/20161/19/2016PPART
DetailsJim Page
Rough to cover inspection performed for underground piping. Partial cover approved for east to west piping, still need thrust block on 90 going to building as well as thrust block for riser inside. Contractor will schedule inspection for the rest of underground when complete.