INSP-Final Inspection | 9/20/2016 | 9/23/2016 | 9/23/2016 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete, hydrostatic test was completed on 06MAY2016
|
INSP-Sprinkler Rough-in | 5/31/2016 | 5/31/2016 | 5/31/2016 | A | PART |
Jim Page
|
|
|
Tenting Inspection complete for overhead fire sprinkler piping in the 3rd level attic spaces as well as 4th level fire sprinkler piping, area's inspected approved for cover with exception to the breeze-ways, the piping crossing the breeze-way an all floors cannot be covered until an approved method is installed to keep this section of piping from freezing
|
INSP-Sprinkler Rough-in/Hydro | 5/5/2016 | 5/6/2016 | 5/6/2016 | A | PART |
Jim Page
|
|
|
Rough to cover inspection complete, 1st level overhead fire sprinkler piping approved for cover with exception to the fire sprinkler piping crossing the breeze-way, the piping crossing the breeze-way an all floors cannot be covered until an approved method is installed to keep this section of piping from freezing. 2nd level overhead fire sprinkler piping approved for cover with exception to breeze-way, 3rd level piping approved for cover will exception to breeze-way and piping that is located in attic space, the piping in th attic space needs to be tented with insulation, once tenting inspection is complete this piping can be covered, 4th level rough in inspection complete, all piping on 4th level cannot be covered until tenting inspection is complete. Any overhead fire sprinkler piping that is covered before tenting inspection will have covering material removed for the inspection.
|
INSP-Sprinkler Rough-in/Hydro | 5/5/2016 | 5/5/2016 | 5/5/2016 | P | CANC |
Jim Page
|
|
|
Please call Jake when you are heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 4/25/2016 | 4/29/2016 | 4/28/2016 | P | CANC |
Jim Page
|
|
|
Please call when you are headed out. Thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 4/20/2016 | 4/26/2016 | 4/25/2016 | P | CANC |
Jim Page
|
|
|
Please call Jake when you are heading out. Thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 3/10/2016 | 3/10/2016 | 3/10/2016 | P | PASS |
Jim Page
|
|
|
Underground rough to cover inspection complete, underground supply approved for cover. Hydrostatic test (200psi for 2 hours)for underground passed/complete.
|