INSP-Final Inspection | 3/28/2017 | 3/28/2017 | 3/28/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Final Inspection | 8/22/2016 | 8/24/2016 | 8/24/2016 | A | PART |
Jim Page
|
|
|
Partial final fire spinkler inspection passed/complete. Each level of the building has fire sprinkler piping that crosses the breezeway, an approved method of keeping the pipe from freezing needs to be installed and inspected before final inspection can be completed. Fire sprinkler inspection is complete for remainder of building. TCO authorized for 60 days per conversation with Scott Arellano.
|
INSP-Sprinkler Rough-in/Hydro | 8/22/2016 | 8/23/2016 | 8/22/2016 | A | CANC |
Jim Page
|
|
|
Please call Anthony when heading out, thank you! Reminder, standpipes and overhead were on two separate permits, both have been scheduled for final. Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Final Inspection | 8/19/2016 | 8/19/2016 | 8/19/2016 | P | FAIL |
Jim Page
|
|
|
Need ball drip on FDC piping in riser room. Backflow needs tamper switches installed. FDC needs caps.
|
INSP-Sprinkler Rough-in | 5/11/2016 | 5/13/2016 | 5/13/2016 | P | PASS |
Jim Page
|
|
|
Tenting inspection for fire sprinkler piping in the attic space of level 3 passed/complete, all piping approved for cover.
|
INSP-Sprinkler Rough-in | 5/10/2016 | 5/11/2016 | 5/11/2016 | A | PART |
Jim Page
|
|
|
Tenting inspection for level 4 complete, overhead fire sprinkler approved for cover on level 4 with exception to the fire sprinkler piping crossing the breezeway, this piping cannot be covered (as well as levels 1,2 and 3) until an acceptable means of keeping the pipe from freezing is inspected and passed.. Tenting for sprinkler piping in attic space on level 3 still not installed, overhead fire sprinkler piping in attic space on level 3 not approved for cover.
|
INSP-Sprinkler Rough-in | 5/9/2016 | 5/10/2016 | 5/10/2016 | A | FAIL |
Jim Page
|
|
|
No tenting on overhead fire sprinkler piping installed at time of inspection, inspection request will need to be scheduled when overhead fire sprinkler tenting is installed.
|
INSP-Sprinkler Rough-in/Hydro | 5/4/2016 | 5/5/2016 | 5/5/2016 | P | CANC |
Jim Page
|
|
|
Please call Jake when you are headed out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 4/18/2016 | 4/21/2016 | 4/22/2016 | P | PART |
Jim Page
|
|
|
200 psi hydrostatic test complete for overhead fire sprinkler piping for all levels. Rough to cover inspection complete for overhead fire sprinkler piping on 1st and 2nd level, 1st and 2nd level approved for cover with exception to piping that is ran through breeze-way, this piping cannot be covered until proper freeze protection is installed and inspected. Partial cover approved for 3rd level fire sprinkler piping, fire sprinkler piping that is not in attic spaces approved for cover with exception to breeze-way piping. Fire sprinkler piping in attic spaces on 3rd level and 4th level cannot be covered until tenting inspection is completed and approved. Fire sprinkler piping crosses the entry corridor on each level, these area's cannot be covered until proper heating/ventilation is provided to keep fire sprinkler piping from freezing through the breeze-way (As addressed and stated on city approved drawings)
|
INSP-Sprinkler Rough-in/Hydro | 3/10/2016 | 3/11/2016 | 3/11/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection complete for underground supply, underground piping approved for cover. Hydrotatic test (200psi for 2 hours) for underground passed/complete.
|
INSP-Sprinkler Rough-in/Hydro | 3/10/2016 | 3/10/2016 | 3/10/2016 | P | FAIL |
Jim Page
|
|
|
Underground hydrostatic test failed, contractor had glued plastic fitting come apart during test. Contractor will reschedule inspection after repair is made.
|