Permit Information
Permit NumberFIR16-00033
StatusFinaled
Name ABSOLUTE FIRE PROTECTION
Site Address 400 S BROADWAY AVE
Project NameWGP1 St. Lukes TI
Customer Number 
ePlanReviewYes
Description
[WGP1 Saint Lukes TI]
The fire sprinkler scope of work consists of remodeling the 6th floor ONLY.

Contractor’s Note:
The scope of work indicates remodel of the 6th floor. (nothing else) There are four drawings. The only drawing reviewed is FP8. The rest of the drawings were treated as reference only. The cross section on drawing FP8 was treated as reference only. If this not the case then a resubmittal is required with a revised scope of work.

Contractor’s Note:
The building permit has not been issued at this time. The building department may determine that changes are required to the building plans in order to meet code. The changes may affect the sprinkler system. The sprinkler contractor will be obligated to make all necessary changes that may be required. Therefore, if the sprinkler contractor chooses to proceed without an issued building permit, they will do so on their own cognizance. This note does not constitute an early start agreement.

(ST. LUKE'S)(MK PLAZA I - ENTIRE BUILDING) Remodel to entire high-rise building including basement and all 6 floors for new office tenant with some assembly uses per approved plans. Work to include demolition of existing tenant spaces on all floors and build back of new spaces on all floors to include new interior walls, doors, interior finish, new suspended ceilings, electrical work, mechanical work, plumbing work and fire protection equipment. Occupant load request for classrooms on 5th floor approved and attached to case. NOTE: This building is fully fire sprinklered for high-rise and atrium provisions. A smoke management system exists for the atrium.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/19/20165/20/20165/20/2016APASS
DetailsJim Page
Final fire sprinkler inspection passed/complete
INSP-Sprinkler Rough-in/Hydro3/22/20163/23/20163/23/2016PPASS
DetailsJim Page
Hydrostatic test (200psi for 2 hours) complete for 6th floor. Rough to cover inspection complete for 6th floor, entire area of work on 6th floor approved for cover.
INSP-Sprinkler Rough-in2/16/20162/17/20162/17/2016APART
DetailsJim Page
Notated areas approved for cover with yellow high-lighter/red ink on city approved drawings. Area's inspected approved for cover.