Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberFIR16-00040
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 400 S CAPITOL BLVD
Project NameResidence Inn
Customer NumberUDG
ePlanReviewYes
Description
[Residence Inn - Boise - UDG only]
The fire sprinkler scope of work consists of two 8” supplies with necessary thrust blocks and fittings.. One supply is connected to West Myrtle Street and the second supply is connected to West Broad Street. The drawing indicates two FDC connections one each on the previously mentions streets.

(RESIDENCE INN BY MARRIOTT) Permit to construct a new 204,396 square foot hotel / restaurant / assembly high-rise building. This building consists of 8 stories of residential hotel above two stories of parking garage / restaurant. A foundation permit was issued for this project under BLD15-02707. Work to include: construction of new rated concrete building, new plumbing, new electrical, new mechanical, new fire sprinklers, new shafts, new interior partitions, and interior finishes in compliance with chapter 8 of the 2012 IBC. This building is to be fully fire sprinklered with an NFPA 13 system and fully alarmed with a NFPA 72 system. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/18/20179/19/20179/19/2017APASS
DetailsJim Page
Final inspection for underground supply passed/complete.
INSP-Supply line flush6/27/20176/30/20176/30/2017ADONE
DetailsJim Page
North supplied underground main line flush complete after repair made
INSP-Sprinkler Rough-in/Hydro6/26/20176/27/20176/27/2017APASS
DetailsJim Page
Hydrostatic test performed after repair was made on the northeast underground supply complete.
INSP-Supply line flush6/14/20176/15/20176/15/2017ADONE
DetailsJim Page
Undergournd flush for south main completed after underground repair was made.
INSP-Sprinkler Rough-in/Hydro6/12/20176/12/20176/12/2017PPART
DetailsJim Page
Hydrostatic test for south underground supply complete.
INSP-Supply line flush6/12/20176/12/20176/12/2017PCANC
DetailsJim Page
Per Jim Page - Schedule for 06/12 Afternoon - Contact will be Ken Orahood ###-####...

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Supply line flush4/18/20174/19/20174/19/2017ADONE
DetailsJim Page
Main supply flushes complete for both underground main feeds.
INSP-Supply line flush4/13/20174/18/20174/18/2017ACANC
DetailsJim Page
Suez was not scheduled for 530 flush time, flush needs to be after hours due to traffic at valve location, flush is rescheduled for 530AM, 19APR2017.
INSP-Sprinkler Rough-in4/11/20174/11/20174/11/2017PPASS
DetailsJim Page
Rough to cover inspection for remaining underground complete, approved for cover.
INSP-Final Inspection4/11/20174/11/20174/11/2017PCANC
DetailsJim Page
Inspection request was for a rough to cover on remaining underground for northside supply, not a final inspection. This inspection request is cancelled and a rough in inspection will be generated.
INSP-Sprinkler Rough-in/Hydro7/25/20167/26/20167/26/2016APART
DetailsJim Page
Partial rough to cover inspection complete for underground supply located on the east side of building. Underground supply installed to the northeast corner of building approved for cover.
INSP-Sprinkler Rough-in/Hydro7/19/20167/20/20167/20/2016PPART
DetailsJim Page
Partial rough to cover inspection for underground supply main that is on the east side of building running north to south complete, area's inspected approved for cover, area that will be inspected at a later date is the remaining underground running north to south on the northeast side of building.
INSP-Sprinkler Rough-in/Hydro7/19/20167/19/20167/19/2016PCANC
DetailsJim Page
Inspection request rescheduled for 20JULY16.
INSP-Sprinkler Rough-in/Hydro7/13/20167/13/20167/13/2016PPART
DetailsJim Page
Partial rough to cover inspection complete for underground main supply located on southside of jobsite, partial cover is approved for underground supply running from west to east on southside of project, change of direction where main turns to go into building will be inspected at later date.