INSP-Final Inspection | 12/16/2016 | 12/16/2016 | 12/16/2016 | P | PASS |
Jim Page
|
|
|
Final underground supply inspection passed/complete.
|
INSP-Supply line flush | 11/17/2016 | 11/22/2016 | 11/22/2016 | A | DONE |
Jim Page
|
|
|
Underground main supply flush complete
|
INSP-Sprinkler Rough-in/Hydro | 11/15/2016 | 11/15/2016 | 11/15/2016 | A | PASS |
Jim Page
|
|
|
Underground supply hydrostatic test complete
|
INSP-Sprinkler Rough-in | 5/26/2016 | 5/27/2016 | 5/27/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply passed/complete, underground approved for cover.
|
INSP-Sprinkler Rough-in | 5/26/2016 | 5/26/2016 | 5/26/2016 | P | PART |
Jim Page
|
|
|
Partial underground cover approved, thrustblocks will be poured at a later date, fittings requiring thrust blocks cannot be covered until thrustblocks are poured.
|
INSP-Sprinkler Rough-in | 2/23/2016 | 2/23/2016 | 2/23/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground stub only, approved for cover. Contractor will schedule inspection for rest of underground when completed.
|