INSP-Final Inspection | 5/19/2016 | 5/20/2016 | 5/20/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete.
|
INSP-Sprinkler Rough-in/Hydro | 4/4/2016 | 4/6/2016 | 4/6/2016 | A | CANC |
Jim Page
|
|
|
Duplicate inspection request, this request cancelled per conversation with point of contact, Jon phone number ###-####.
|
INSP-Sprinkler Rough-in/Hydro | 4/4/2016 | 4/5/2016 | 4/5/2016 | A | PART |
Troy Cobbley
|
|
|
The 5th floor hydro test passed. Also the rough-in inspection for the gridded areas passed. Piping above the gridded areas can be covered. One branch line restraint installed while I waited.
|
INSP-Sprinkler Rough-in/Hydro | 4/4/2016 | 4/4/2016 | 4/4/2016 | P | CANC |
Troy Cobbley
|
|
|
Rescheduled for tomorrow morning
|
INSP-Sprinkler Rough-in | 2/25/2016 | 2/26/2016 | 2/26/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection complete for hard-lids on 5th floor, hard-lids approved for cover.
|