INSP-Final Inspection | 9/1/2016 | 9/2/2016 | 9/2/2016 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Seth Phone #: ###-####
|
INSP-Final Inspection | 8/8/2016 | 8/9/2016 | 8/9/2016 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy is ok for life safety with Scott's permission. I need as-builts, testing of elevator car #1 and the map at the facp.
|
INSP-Alarm Testing | 8/5/2016 | 8/8/2016 | 8/8/2016 | A | DONE |
Troy Cobbley
|
|
|
Need data sheets, breaker locks and locations, test flow switches, test outside alarm bell, document box, map at the facp, test elevator recall
|
INSP-Final Inspection | 8/5/2016 | 8/5/2016 | 8/5/2016 | P | FAIL |
Troy Cobbley
|
|
|
Due to problems on the fire alarm system todays inspection was a walk through of the devices on the 4th and 3rd floors. I noted the need for as-builts due to added smoke detectors and the need for weather proof back boxes on the audio/visual devices installed in the restrooms with showers. Contractor did not have any of the small documents which included the data sheets and review notes.
|