INSP-Final Inspection | 3/7/2017 | 3/7/2017 | 3/7/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Final Inspection | 10/20/2016 | 10/20/2016 | 10/20/2016 | P | PART |
Jim Page
|
|
|
Final fire sprinkler inspection for levels 3 & 4 complete. FIR permit will stay in issued status (Partial final for records) until BLD permit is ready to be finaled on life fire safety, at time of life fire safety completion FIR permit will be finaled as well.
|
INSP-Sprinkler Rough-in/Hydro | 5/10/2016 | 5/10/2016 | 5/10/2016 | A | PART |
Jim Page
|
|
|
Rough to cover inspection complete for level 4, level 4 approved for cover. 200 psi hydrostatic test complete for level 4.
|
INSP-Sprinkler Rough-in/Hydro | 5/6/2016 | 5/9/2016 | 5/9/2016 | A | CANC |
Jim Page
|
|
|
Inspection request cancelled per coversation with point of contact on project. Rough-in/Hydro request will be rescheduled to coincide with early morning main line flush.
|
INSP-Sprinkler Rough-in | 4/18/2016 | 4/18/2016 | 4/18/2016 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete for 3rd floor. Notated city approved plans area's that were inspected with red ink/yellow highlighter, area's notated on city approved drawings approved for cover.
|