INSP-Final Inspection | 9/22/2016 | 9/23/2016 | 9/23/2016 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Supply line flush | 9/22/2016 | 9/23/2016 | 9/23/2016 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in/Hydro | 3/30/2016 | 3/31/2016 | 3/31/2016 | A | PASS |
Jim Page
|
|
|
Underground hydrostatic test complete, underground rough to cover inspection passed/complete, underground approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 2/22/2016 | 2/23/2016 | 2/23/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground stub in for building supply complete, approved for cover. 200 psi for 2 hour hydrostatic test complete for installed underground piping.
|
INSP-Sprinkler Rough-in/Hydro | 2/22/2016 | 2/22/2016 | 2/22/2016 | P | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with point of contact, Mike phone ###-#### , contractor no ready for hydrostatic test, inspection will be scheduled for later date.
|