INSP-Final Inspection | 6/24/2016 | 6/27/2016 | 6/27/2016 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection passed/complete.
|
INSP-Final Inspection | 6/17/2016 | 6/20/2016 | 6/20/2016 | P | PART |
Jim Page
|
|
|
Elevator recall/shunt tested, Audio visual devices tested on level 1, items left for inspection: smoke evacuation system and elevator smoke curtains.
|
INSP-Final Inspection | 6/16/2016 | 6/17/2016 | 6/17/2016 | P | CANC |
Jim Page
|
|
|
Inspection request will be rescheduled 20June2016 due to medical emergency with the inspector.
|
INSP-Final Inspection | 6/8/2016 | 6/10/2016 | 6/10/2016 | A | PART |
Jim Page
|
|
|
Alarm inspection for audio visuals complete for level 3, level 2 and basement level. Final items to test/inspect, level one A/V's, smoke evacuation system for all levels, elevator smoke curtians, elevator recall and elevator shunt
|
INSP-Alarm Testing | 6/1/2016 | 6/2/2016 | 6/2/2016 | A | DONE |
Jim Page
|
|
|
Alarm inspection/testing for level 4 complete, contractor had some A/V devices on 3rd floor disconnected (northeast corner class room, total of 4 A/V's), will need to perform inspection for disconnected devices when level 2 is inspected.
|
INSP-Final Inspection | 5/19/2016 | 5/20/2016 | 5/20/2016 | A | PART |
Jim Page
|
|
|
Project is being inspected in phases, todays inspection consisted of tamper and waterflow switches for penthouse sprinklers, 6th floor sprinklers and 5th floor sprinklers, all devices operated correctly. Audio/Visual devices tested for 6th floor and 5th floor, all AV's operated correctly. Contractor will schedule inspections for other floors when they are ready.
|