INSP-Final Inspection | 6/8/2016 | 6/10/2016 | 6/10/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for level 2 complete.
|
INSP-Final Inspection | 6/8/2016 | 6/9/2016 | 6/8/2016 | A | CANC |
Jim Page
|
|
|
Jon Beazer is site contact Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
|
INSP-Sprinkler Rough-in/Hydro | 5/24/2016 | 5/25/2016 | 5/25/2016 | A | CANC |
Jim Page
|
|
|
Inspection request was for basement level, this inspection request cancelled and a new inspection request generated.
|
INSP-Sprinkler Rough-in/Hydro | 5/6/2016 | 5/9/2016 | 5/9/2016 | P | PASS |
Jim Page
|
|
|
200 psi hydrostatic test for overhead fire sprinkler piping located on level 2 complete.
|
INSP-Sprinkler Rough-in | 4/4/2016 | 4/6/2016 | 4/6/2016 | A | CANC |
Jim Page
|
|
|
Duplicate inspection request, this request cancelled per conversation with point of contact, Jon phone number ###-####.
|
INSP-Sprinkler Rough-in/Hydro | 4/4/2016 | 4/5/2016 | 4/5/2016 | A | PART |
Troy Cobbley
|
|
|
The 2nd floor piping above the hardlids/corridors is ok to cover. Rough-in passed.
|
INSP-Sprinkler Rough-in | 4/4/2016 | 4/4/2016 | 4/4/2016 | P | CANC |
Troy Cobbley
|
|
|
Rescheduled for tomorrow morning
|